Construction milestones

30 June 2013

Injector infrastructure done

Technical infrastructure in the injector buildings XSIN, XTIN, XHIN is complete and ready for machine component installation

31 August 2013

LINAC infrastructure done

Technical infrastructure in the buildings XHM, XHEE, XSEE, XTL is complete and ready for machine component installation

30 June 2014

Injector tunnel closed

Technical commissioning of warm injector done. Injector is ready to be cooled down in order to take beam

30 September 2014

First beam to Injector dump

Beam has been passed through the injector from the gun all the way to the injector dump

30 September 2014

SASE1/3 infrastructure done

Technical infrastructure in the buildings XHE1, XS1, XS3, XHE3, XSDU2, XTD2, XTD4, XTD9, XTD10 is complete and ready for machine component installation

30 September 2014

XHEXP1 infrastructure done

Technical infrastructure in the buildings XHEXP1, XHVAC, XHPSC is complete and ready for machine component installation

30 April 2015

SASE2 infrastructure done

Technical infrastructure in the buildings XS2, XHE2, XS4, XHE4, XSDU1, XTD1, XTD3,XTD5, XTD6, XTD7, XTD8 is complete and ready for machine component installation

30 June 2015

Linac tunnel closed

Technical commissioning of warm linac done. LinacĀ is ready to be cooled down in order to take beam

31 August 2015

SASE1 Instruments ready for beam

The SASE1 instruments are ready to open the beam shutters

30 September 2015

First beam to XS1 Dump

Beam has been passed through the linac from injector all the way to the main dump

30 September 2015

XTD2, XTD4, XTD9, XTD10 closed

Technical commissioning is complete and this machine section is ready to take beam

15 October 2015

Beam to XSDU2

Beam has been passed through the SASE1/3 electron beam line all the way to XSDU2

15 December 2015

First Lasing SASE1 possible

First SASE1 (SPB & FXE) Photons in XHEXP1 possible

31 January 2016

SASE3 Instruments ready for beam

The SASE3 instruments are ready to open the beam shutters

31 January 2016

First Lasing SASE3 possible

First SASE3 (SQS &SCS) Photons in XHEXP1 possible

31 March 2016

Start Operation

Sufficient equipment is installed and commissioned. The accelerator and the SASE1 beam line achieve the following parameters:

  • Wavelength < 0.2 nm
  • Peak brilliance > 1030 Photons/s/mm2/mrad2/0.1 % BW
  • Dimension at sample < 1 mm2 (FWHM)
  • Positional Stability < 50 % of beam size (RMS)
  • Photon Energy Stability < 0.1 %
  • Shot-to-shot Intensity Fluctuation < 10

31 March 2016

SASE1 Instruments users operation

First user experiment at SASE1 (SPB & FXE) possible

31 March 2016

XTD1, XTD3, XTD5, XTD7, XTD8 closed

Technical commissioning is complete and this machine section is ready to take beam

31 March 2016

SASE2 Instruments ready for beam

The SASE2 instruments are ready to open the beam shutters

15 April 2016

Beam to XSDU1

Beam has been passed through the SASE2 electron beam line all the way to XSDU1

30 April 2016

SASE3 Instruments user operation

First user experiment at SASE3 (SQS & SCS) possible

31 May 2016

XTD6, closed

The SASE2 photon beam line is complete and this machine section is ready to take beam

30 June 2016

First Lasing SASE2 possible

First SASE2 (MID & HED) Photons in XHEXP1 possible

31 October 2016

SASE2 Instruments user operation

First user experiment at SASE2 (MID & HED) possible

December 2017

Extended beam delivery

Extended beam delivery specification reached with delivery of full number of hours under user operation conditions