30 June 2013 |
Injector infrastructure done Technical infrastructure in the injector buildings XSIN, XTIN, XHIN is complete and ready for machine component installation |
31 August 2013 |
LINAC infrastructure done Technical infrastructure in the buildings XHM, XHEE, XSEE, XTL is complete and ready for machine component installation |
30 June 2014 |
Injector tunnel closed Technical commissioning of warm injector done. Injector is ready to be cooled down in order to take beam |
30 September 2014 |
First beam to Injector dump Beam has been passed through the injector from the gun all the way to the injector dump |
30 September 2014 |
SASE1/3 infrastructure done Technical infrastructure in the buildings XHE1, XS1, XS3, XHE3, XSDU2, XTD2, XTD4, XTD9, XTD10 is complete and ready for machine component installation |
30 September 2014 |
XHEXP1 infrastructure done Technical infrastructure in the buildings XHEXP1, XHVAC, XHPSC is complete and ready for machine component installation |
30 April 2015 |
SASE2 infrastructure done Technical infrastructure in the buildings XS2, XHE2, XS4, XHE4, XSDU1, XTD1, XTD3,XTD5, XTD6, XTD7, XTD8 is complete and ready for machine component installation |
30 June 2015 |
Linac tunnel closed Technical commissioning of warm linac done. LinacĀ is ready to be cooled down in order to take beam |
31 August 2015 |
SASE1 Instruments ready for beam The SASE1 instruments are ready to open the beam shutters |
30 September 2015 |
First beam to XS1 Dump Beam has been passed through the linac from injector all the way to the main dump |
30 September 2015 |
XTD2, XTD4, XTD9, XTD10 closed Technical commissioning is complete and this machine section is ready to take beam |
15 October 2015 |
Beam to XSDU2 Beam has been passed through the SASE1/3 electron beam line all the way to XSDU2 |
15 December 2015 |
First Lasing SASE1 possible First SASE1 (SPB & FXE) Photons in XHEXP1 possible |
31 January 2016 |
SASE3 Instruments ready for beam The SASE3 instruments are ready to open the beam shutters |
31 January 2016 |
First Lasing SASE3 possible First SASE3 (SQS &SCS) Photons in XHEXP1 possible |
31 March 2016 |
Start Operation Sufficient equipment is installed and commissioned. The accelerator and the SASE1 beam line achieve the following parameters:
|
31 March 2016 |
SASE1 Instruments users operation First user experiment at SASE1 (SPB & FXE) possible |
31 March 2016 |
XTD1, XTD3, XTD5, XTD7, XTD8 closed Technical commissioning is complete and this machine section is ready to take beam |
31 March 2016 |
SASE2 Instruments ready for beam The SASE2 instruments are ready to open the beam shutters |
15 April 2016 |
Beam to XSDU1 Beam has been passed through the SASE2 electron beam line all the way to XSDU1 |
30 April 2016 |
SASE3 Instruments user operation First user experiment at SASE3 (SQS & SCS) possible |
31 May 2016 |
XTD6, closed The SASE2 photon beam line is complete and this machine section is ready to take beam |
30 June 2016 |
First Lasing SASE2 possible First SASE2 (MID & HED) Photons in XHEXP1 possible |
31 October 2016 |
SASE2 Instruments user operation First user experiment at SASE2 (MID & HED) possible |
December 2017 |
Extended beam delivery Extended beam delivery specification reached with delivery of full number of hours under user operation conditions |